HUAWEI USG6000E Series
Hardware Guide
Procedure
Step 1 Ensure that the PGND cable is adequately grounded.
Step 2 Connect power cables for the two DC power modules one after the other.
● Note the labels on the DC power cables to avoid misoperations.
● To improve availability, connect two power modules to different power sources.
1.
2.
----End
Follow-up Procedure
Verify the following after the connection is complete:
Issue 08 (2022-04-20)
NO TICE
Plug the connector end of the DC power cable to the DC power module.
Connect the other end of the DC power cable to the output of the power
supply device in the equipment room.
Figure 5-35 Connecting DC power cables
The power cables are correctly and firmly connected to the power supply
device.
If multiple USGs are deployed, the power cables of each USG are correctly
labeled for distinction.
Copyright © Huawei Technologies Co., Ltd.
5 Hardware Installation
558