UPS5000-H-(400 kVA-800 kVA)
User Manual (100 kVA Power Modules)
Figure 6-21 Installing signal cables between the UPS and the SmartLi
(1) Monitoring interface unit in the master SmartLi cabinet
----End
6.3.2 Installing the UPS + Bottom Cabling Cabinet
6.3.2.1 Installing Cabinets
Installation on the Floor
Ensure that the installation floor is level.
Step 1 Determine the cabinet installation positions on the floor based on the holes in the
marking-off template for floor installation.
Issue 03 (2021-08-03)
NO TICE
NO TE
● A: mounting holes on the channel steel
● B: mounting holes on the floor
Copyright © Huawei Technologies Co., Ltd.
6 Installation