400 kva-800 kva. 100 kva power modules
Hide thumbs Also See for UPS5000-H:
Table of Contents

Advertisement

UPS5000-H-(400 kVA-800 kVA)
User Manual (100 kVA Power Modules)
Knock the expansion bolts into the holes until the expansion sleeves completely fit
into the holes. The expansion sleeves must be completely buried under the ground
to facilitate subsequent installation.
Figure 6-53 Drilling holes and installing expansion sleeves
(1) M12 bolt
(4) Expansion sleeve
Step 3 Move the cabinet to the installation position.
Step 4 Secure the cabinets.
Figure 6-54 Securing the cabinets
Step 5 Install anchor baffle plates.
Issue 03 (2021-08-03)
NO TICE
Copyright © Huawei Technologies Co., Ltd.
(2) Spring washer
(5) Expansion nut
6 Installation
(3) Flat washer
(6) Concrete floor