Procedure
Step 1 Take out OT terminals and cord end terminals from the fittings bag, and prepare cables.
Step 2 Connect power cables, as shown in the following figure.
Exercise caution while connecting cables. Prepare protective tools in advance.
Figure 3-28 Connecting power cables
1.
2.
3.
4.
Step 3 Use a multimeter to check for a short circuit between L and N of AC1 and AC2. Use a
multimeter to check for a short circuit between L, N, and PE.
Step 4 Check that the cable connections are secure.
Issue 07 (2020-03-16)
Crimp the cables firmly and ensure that they are not loose after pulling.
If the cables are not recommended specifications, you need to prepare the terminals by
yourself.
Connect the cables with crimped terminals to the L, N, and PE shown in
Remove screws from both ends of the clip to remove it.
Place the connected power cables vertically, use the clip to secure them in a proper
position, and use screws to secure the clip.
Fasten the power cable to the vertical pillar by cable ties every 150 mm to 200 mm.
If there is a short circuit, remove the cable and reconnect it using the method described
in
Step
2.1. After verifying the connection, perform
If there is no short circuit, perform
Copyright © Huawei Technologies Co., Ltd.
Step
4.
Step
4.
3 Installation
Figure
3-28.
52

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netcol5000-c065Netcol5000-c080

Table of Contents