Figure 8-15 Temperature and humidity setting screen
Step 4 Verify the temperature and humidity settings by referring to the air-cooled cooling product
temperature and humidity initial configuration table.
If any initial configuration is inconsistent with the initial setting, change it to the initial
setting.
----End

8.3 Commissioning Monitoring Components

8.3.1 Preparations and WebUI Login

Prerequisites
Procedure
Step 1 Connect a network cable between the PC network port and the WAN_1 port (protected by a
security mechanism) on the ECC800.
Table 8-6 Default IP addresses for the WAN and LAN ports on the ECC800
Port
WAN_1
WAN_2
LAN_1 and LAN_2
Issue 04 (2020-01-17)
Computer operating system: Windows 7 and later versions
It is recommended that the screen resolution be 1366 x 768 or higher.
Browser: IE9 and later versions; Firefox and later versions; Chrome and later versions
Copyright © Huawei Technologies Co., Ltd.
8 Commissioning Core Components
Default IP Address
192.168.1.10
192.168.0.10
192.168.248.10