Preparing For The Fire Extinguishing System Power-On Commissioning - Huawei FusionModule1000A40 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
4.7 Preparing for the Fire Extinguishing System Power-On
Commissioning
Prerequisites
The FusionModule1000 has been installed.
Preparations
Tools: none
Documents: fire extinguishing device layout diagram (CE), fire extinguishing system
conceptual diagram (CE)
Skill requirement: fire engineer
For the diagrams and tables, see the initial configuration parameter manual for the solution in
use.
Procedure
Step 1 Understand the layout of fire extinguishing devices by referring to the fire extinguishing
device layout diagram.
Step 2 Understand the running of the fire extinguishing system by referring to the fire extinguishing
system conceptual diagram.
----End
Issue 04 (2020-01-17)
Copyright © Huawei Technologies Co., Ltd.
4 Preparations for Power-On Commissioning
22