Preparing For The Management System Power-On Commissioning - Huawei FusionModule1000A40 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
Step 6 Check the pipe connections of the air-cooled smart cooling products. Verify that the
secondary refrigerant circulation pipeline, secondary refrigerant water refill pipeline,
humidifier water refill pipeline, and condensate drainpipe are installed as required, and that
the thermal insulation layer is intact.
Step 7 Verify that the required amount of refrigerant is injected into the cooling system.
Step 8 Check the auxiliary water refill devices, and verify that water refill to the humidifier is
normal.
Step 9 Verify that the condensate drainpipe is not blocked.
Step 10 Check the FusionModule1000 aisle containment, and verify that the doors, floors, and ceilings
are properly sealed.
----End
4.6 Preparing for the Management System Power-On
Commissioning
Prerequisites
The FusionModule1000 has been installed.
Preparations
Tools: network cable tester, Phillips screwdriver, small-sized flat-head screwdriver,
multimeter, ESD wrist strap
Documents: monitoring device layout diagram, monitoring device networking diagram,
management system initial configuration table
Skill requirement: weak-current engineer familiar with the management system
Procedure
Step 1 Understand the layout of monitoring devices by referring to the monitoring device layout
diagram.
Step 2 Understand the connections of the management system by referring to the monitoring device
networking diagram.
Step 3 Understand the initial configurations of the management system by referring to the
management system initial configuration table.
The passwords and parameters must be the same as those in the initial configuration
parameter manual for the solution in use.
----End
Issue 04 (2020-01-17)
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.