When powering on and commissioning the air cooled smart cooling product, you are not
allowed to modify the initial configurations of the air cooled smart cooling product unless you
are authorized by onsite Huawei engineers.
Step 4 Tap Indicates on the main screen, and tap Confirm on the dialog box that appears. If the start
succeeds, the system prompts that the command is successfully executed.
----End

8.2.1 Initial DIP Switch Configuration for T/H Sensors

Prerequisites
You have powered on the air-cooled smart cooling products.
Preparations
Tool: flat-head screwdriver, step ladder
Document required: cooling device initial configuration table
Skill requirement: cooling engineer
Context
Each smart cooling product is configured with three remote T/H sensors in the cold aisle.
You need to set the DIP switches for the remote T/H sensors using these sensors.
shows the DIP switch on a remote T/H sensor.
Figure 8-5 DIP switch on a remote T/H sensor
Issue 04 (2020-01-17)
Air-cooled smart cooling products include 21 kW and 25 kW models. The DIP switch
setting methods for the two models are the same. For details, see the cooling device initial
configuration table.
For the table, see the initial configuration parameter manual for the solution in use.