Prerequisites
Preparations
Tools: none
Document: initial configuration parameter manual
Skill requirement: power distribution engineer
Procedure
Step 1 Switch on the external input circuit breaker.
Step 2 Switch on the power supply circuit breaker by referring to the power supply and distribution
system diagram, and power on the FusionModule1000 level by level.
Step 3 Verify that the power-on process is normal.
Issue 04 (2020-01-17)
6
You have prepared for the power-on commissioning.
You have verified all the specifications for the power-on.
You have put on protective articles.
Before the lighting system is powered on, prepare a portable light or open some of the
pre-fab. module doors.
Circuit breakers of various specifications are reserved in the power supply system. If any
of these circuit breakers are used, conduct proper operations on them for the
commissioning.
For equipment with dual power inputs, circuit breakers of both power inputs must be switched on.
Copyright © Huawei Technologies Co., Ltd.