Initial Configuration Of Temperature And Humidity - Huawei FusionModule1000A40 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide

8.2.4 Initial Configuration of Temperature and Humidity

Prerequisites
You have powered on the air-cooled smart cooling products.
Preparations
Tools: none
Documents: management system initial configuration table, cooling device layout diagram,
cooling device initial configuration table
Skill requirement: cooling engineer
Context
Cooling products in one module constitute a group. You need to set the temperature and
humidity of the cooling product system on the master unit in each group before cooling
products in the group are used.
Procedure
Step 1 Tap Settings > System Settings on the main screen to enter the page shown in
Issue 04 (2020-01-17)
Air-cooled smart cooling products include 21 kW and 25 kW models.
For the diagrams and tables, see the initial configuration parameter manual for the solution
in use.
To change the settings, you need to log in as the Admin user. For the password, see the management
system initial configuration table.
You need to obtain permission before changing system settings. Only trained and qualified personnel
can change settings excluding the control type and set point of the T/H sensor.
Copyright © Huawei Technologies Co., Ltd.
8 Commissioning Core Components