Commissioning Core Components; Commissioning The Ups; Commissioning The Integrated Ups - Huawei FusionModule1000A40 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
8

8.1 Commissioning the UPS

8.1.1 Commissioning the Integrated UPS

Prerequisites
Preparations
Tool: multimeter
Documents: integrated UPS user manual, power supply and distribution device layout
diagram, power supply and distribution system diagram, power supply and distribution device
initial configuration table
Skill requirement: power distribution engineer
Procedure
Step 1 (Optional) Switch on the ATS control loop (Q1 and Q2 in the left lower part at the rear of the
cabinet) to power on the ATS.
Step 2 Switch on the general input circuit breaker and the input power circuit breaker of the
integrated UPS to power on the integrated UPS.
Issue 04 (2020-01-17)

Commissioning Core Components

The upstream circuit breaker PDB of the integrated UPS has been powered on.
Power modules and batteries have been installed and connected, and the installation has
been verified.
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
This step applies only to the 40 ft N+X scenario.
Copyright © Huawei Technologies Co., Ltd.
8 Commissioning Core Components
45