Commissioning The Emergency Light (Ce) - Huawei FusionModule1000A40 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
Preparations
Tools: none
Documents: power supply and distribution system diagram, documents delivered with the
extinguishant control panel, fire extinguishing system conceptual diagram (CE), fire
extinguishing device layout diagram (CE)
Skill requirement: fire engineer
Procedure
Step 1 Switch on the input power circuit breaker of the extinguishant control panel or connect the
extinguishant control panel batteries to power on the extinguishant control panel.
Step 2 Flip the key to Enable Control rightward, and set the access level of the extinguishant
control panel to 2.
Step 3 Press Silence/Sound Alarm to start or abort the fire alarm bell.
Step 4 Press Alarm/Fault Warning Silence to silence the fault noise generated by the extinguishant
control panel.
Step 5 Press Reset to reset the extinguishant control panel, and reset the key to Enable Control by
flipping it leftward.
----End

8.4.2 Commissioning the Emergency Light (CE)

Prerequisites
The sockets of the emergency light have been powered on.
Preparations
Tools: step ladder, Phillips screwdriver
Documents: power supply and distribution system diagram, fire extinguishing device layout
diagram (CE)
Skill requirement: fire engineer
Procedure
Step 1 Turn off the upstream switch of the emergency light power cable.
Issue 04 (2020-01-17)
For the diagrams, see the initial configuration parameter manual for the solution in use.
For the diagrams, see the initial configuration parameter manual for the solution in use.