Check Before Power-On - Huawei FusionModule1000A40 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
Preparations
Tools: multimeter, screwdriver, step ladder, insulation megohmmeter, pressure gauge
Document: initial configuration parameter manual
Skill requirement: power distribution engineer

Check Before Power-On

Table 5-1 Items to be checked before power-on
System
Check Item
Integrated
Connecting
cabling
cables
Power supply
ATS status
and
distribution
system
Power cable
insulation
Issue 04 (2020-01-17)
5
Check Before Power-On
Operation Method
Check cable connections.
Check the cable layout.
Check the cable labels.
Verify ATS settings and remove
the ATS handle.
Measure the insulation of the
power cables using an insulation
megohmmeter.
Copyright © Huawei Technologies Co., Ltd.
5 Check Before Power-On
Reference
Cables are neat, tidy not coiled, and
excessive parts are cut.
Power cables are at least 20 mm
away from signal cables.
Power cables are bound at intervals
of at most 200 mm. For thicker
cables, the intervals can be greater.
Cable ties do not overlap, and the
joints are evenly cut without burrs.
Cables are placed properly and not
tense at turning points.
Cable routes are straight and
smooth, and do not intersect inside
a cabinet.
Cables are securely connected.
The ATS handle has been removed.
The motor operation mechanism is
set to
.
There is no electricity leakage in the
power supply and distribution system.