Figure 4-11 Removing the screws that secure the intelligent heat exchanger to the pre-fab. module
Step 4 Replace the faulty intelligent heat exchanger with a new one.
To prevent injury, at least two persons are required to move the intelligent heat exchanger.
Step 5 Tighten the screws and connect the cables.
----End
Follow-up Procedure
Dispose of the removed intelligent heat exchanger that is confirmed faulty.

4.3 Replacing Monitoring System Components

4.3.1 Replacing an ECC800 Main Control Module

Prerequisites