FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
7.3 The Management System Commissioning
Before putting the FusionModule1000 into use, you must commission the management
system to ensure normal running.
7.3.1 Preparing for Commissioning the Management System
Tool Preparations
Multimeter, network cable tester, and RJ45 crimping tool
(Optional) Preparations for Modifying the Management System Initial
Configurations
As the management system parameters are complex, you are not allowed to modify the initial
configurations unless you are authorized by an appropriate person.
Initial configurations have been made for the FusionModule1000 management system before
delivery. To modify the initial configurations of the management system, make the following
preparations:
1.
2.
3.
7.3.2 Commissioning the Management System
Prerequisites
The FusionModule1000 is powered on, commissioned, and working properly.
During the commissioning, if any alarm is raised, clear the alarm before continuing the
commissioning.
Preparations
Tool: network cable tester
Documents: monitoring device layout diagram, management system initial configuration table
Issue 04 (2020-01-17)
Read through all related management system documents and get familiar with the
detailed management system configurations, configuration method, and operating
principles.
Get familiar with the initial configuration parameters of the management system by
referring to the management system initial configuration table in the initial configuration
parameter manual.
Modify the parameters for the management system based on the initial configuration
table, and save a copy for future reference.