Power-On Commissioning; Preparing For Power-On; Powering On The Unit - Huawei FusionCol8000-C210 User Manual

In-room chilled water smart cooling product
Hide thumbs Also See for FusionCol8000-C210:
Table of Contents

Advertisement

FusionCol8000-C210 In-room Chilled Water Smart
Cooling Product
User Manual

5.1 Preparing for Power-On

Procedure
Step 1 Check that the AC/DC auxiliary power module, main control module and fan drive
module are inserted properly and the latches are locked.
Step 2 Check that the fan switches QF3–QF6 and electric heater switch QF7 (optional)
are turned on and the smart cooling product is properly grounded.
Step 3 Verify that the input voltage meets the requirement.
Step 4 Verify that the indoor unit power cable is connected properly.
Step 5 If teamwork networking is required, verify that the teamwork cable is correctly
connected.
Step 6 Verify that the cable connections and DIP switch settings of the T/H sensors are
correct.
Step 7 Turn on the general switch. For a unit that has two power inputs, turn on the
active power switch QF1 and standby power switch QF2.
----End

5.2 Powering On the Unit

Procedure
Step 1 Turn on the general switch, upstream switch, (optional) electric heater switch QF7,
and fan switches QF3–QF6. For a unit that has two power inputs, turn on the
active power switch QF1 and standby power switch QF2.
Step 2 After the initial power-on, the Quick Settings screen is displayed. Log in as user
admin, as shown in
Issue 05 (2022-12-15)
5

Power-On Commissioning

Figure
Copyright © Huawei Digital Power Technologies Co., Ltd.
5-1.
5 Power-On Commissioning
74