FusionCol8000-C210 In-room Chilled Water Smart
Cooling Product
User Manual
2.
4.3.6 (Optional) Connecting the Air Duct
An air duct needs to be prepared onsite based on site requirements.
Procedure
Step 1 Remove the eight M6x16 bolts from both sides of the unit.
Step 2 The air duct is secured to the top of the unit using M4x12 bolts, and is secured to
both sides of the air duct using M6x25 bolts.
Issue 05 (2022-12-15)
Secure the unit.
a.
Secure the unit to the ground or base using four M12 bolts.
b.
Secure the anchor baffle plate to the fan side using eight M5x10 tapping
screws.
NO TE
● If the air duct is not connected, seal the fan side.
● Obtain the anchor baffle plates according to the packing list.
Figure 4-13 Securing the unit to the floor
Figure 4-14 Securing the unit to a base
NO TE
After the unit is secured, seal the base on the fan side.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 System Installation
47