User Manual
Non-initial Startup
Step 1 Tap Start on the home screen.
●
●
----End
5.7 Wizard Startup
Context
Wizard Startup allows for commissioning of components such as the fan, electric
heater, humidifier, and chilled water valve. It also supports automatic operation
and checking of components, and can output a commissioning report.
After initial power-on and startup, the screen displays the Wizard Startup screen.
You can choose to start commissioning now. You can also choose Maint > Wizard
Startup to start commissioning in future.
Tapping No or Exit, submission timeout, and system exception all result in
commissioning failures. Choose Maint > Wizard Startup to enter the Wizard
Startup screen for new commissioning.
Procedure
Step 1 On the home screen, choose Maint > Wizard Startup, as shown in
Issue 05 (2022-12-15)
If the Password required for start or shutdown onsite function is enabled,
enter the login password to start the unit.
Figure 5-15 Requiring a startup password
If the Password required for start or shutdown onsite function is not
enabled, tap OK to start the unit.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Power-On Commissioning
Figure
5-16.
98