Before installing the pipe, release all nitrogen from the pipe to avoid personal
injury.
● The chilled water pipes should be closely wrapped with thermal insulation
foam (the thickness is less than 20 mm) along the route. Ensure that the foam
is in close contact with the pipes.
● After pipes are routed for the unit, seal the gaps between the pipes and the
pipe holes.
● Connect pipes routed from the top onsite. Do not remove the side pipe plug.
To minimize the noise due to vibration of the unit, perform the following
operations:
Figure 4-18 Fastener layout (unit: mm)
Table 4-3 Chilled water pipe port diameter
Model
FusionCol8000-C
Procedure
Step 1 Remove the top hole cover.
Issue 05 (2022-12-15)
CA UTION
NO TICE
When the routing direction of the chilled water pipe is changed, add a
fastener at the position that is 1000 mm away from the changing point.
When the chilled water pipe is straight, add a fastener every 2500 mm.
NO TE
Onsite personnel prepare the required materials and install the fasteners.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Chilled Water Inlet Pipe
Outer Port Diameter
G 2-in, thread
connection
4 System Installation
Chilled Water Outlet
Pipe Outer Port
Diameter
G 2-in, thread
connection