4.1 Installation Requirements

4.1.1 Transportation

Transportation Precautions
The unit is very heavy and needs to be hoisted onsite. A sufficient operation
platform and space are required.
The unit installation and hoisting are complicated due to the uncertainty of the
time when the unit enters the site, limited inventory onsite, multiple cross
operations, and limited operation space. Therefore, various protection measures
need to be taken to avoid damage to the unit and the finished products onsite.
Difficulties in Transportation and Construction

4.1.2 Storage

Before installing the unit, place it in a dry, rainproof, fireproof, and anticorrosive
environment.
Issue 05 (2022-12-15)
Difficult hoisting: In outdoor scenarios, it is difficult to hoist and move the
unit because it is heavy.
The foundation for the unit base is not prepared in advance and the unit
needs to be hoisted for multiple times. The corresponding protection platform
needs to be set up and removed for multiple times. This may even affect
normal construction in the related space.
The space for stacking the unit onsite is limited, but the precision requirement
for the positioning of the unit is high. Therefore, the hoisting personnel, unit
manufacturer, and onsite installation personnel need to closely cooperate with
each other for a long time.
Ensure that it is free from dirt, rain, snow, or animal intrusion, and that the
protective film on the surface is intact.