5.2 Fire Extinguishing System Commissioning (3C)

Prerequisites
● Before commissioning the fire extinguishing system, disconnect all control
cables to the electromagnetic valve of the fire extinguisher cylinder to avoid
extinguishant release and damage to equipment due to misoperations during
the commissioning. After the commissioning is completed, reconnect cables to
the electromagnetic valve.
● Do not remove the safety pin before the fire extinguishing system is
commissioned; otherwise, extinguishant may be released by mistake.
● To avoid damaging the detector probe, keep a proper distance between the
heating device and the heat detector.
Preparations
Tools: multimeter, smoke pistol, heating device, Phillips screwdriver, flat-head
screwdriver
Documents: fire extinguishing system conceptual diagram (standard), fire
extinguishing device layout diagram (standard)
Skill requirement: fire engineer
Procedure
Step 1 Press and hold the ON/OFF key on the encoder for 1 second to start the encoder.
Step 2 Press # to switch the mode. When 324 is displayed on the screen, use a dedicated
external connection cable to connect the terminal device and set the address code
for the device on the bus.
Issue 02 (2022-12-15)
The fire alarm control panel has been powered on.
The management system is working properly.
D ANGER
NO TE
For the diagrams, see the initial configuration parameter manual for the solution in use.
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 System Commissioning
66

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents