Manual operations for opening
and closing the circuit-breaker
159 | © 2023 ABB | 1SDH001330R1002 - ECN000297030
The following is the sequence of steps for closing and opening the circuit-breaker:
1.
Check that the circuit-breaker is open (open / closed indicator "O - OPEN"), and check that the
springs are discharged (spring signalling device "white - DISCHARGED SPRING") as indicated in
Figure 74.
2.
Charging the springs - Pull the lever [A] downwards several times until the springs charged
signalling device [B] is "yellow - CHARGED SPRING" as indicated in Figure 75.
Figure 74
3.
Check that the circuit-breaker is open (open/closed signalling device "O - OPEN"), and check that
the springs are charged (springs signalling device "yellow - CHARGED SPRING") as indicated in
Figure 76.
4.
Closing - Press the closing pushbutton "I - Push ON" as indicated in Figure 77.
Figure 76
5.
Check that the circuit-breaker is closed (open/closed indicator "I - CLOSED"), and check that the
springs are discharged (spring signalling device "white - DISCHARGED SPRING" as indicated in
Figure 78.
6.
Opening - Press the opening pushbutton "O - Push OFF" as indicated in Figure 79.
Figure 78
A
B
Figure 75
Figure 77
Figure 79
Continued on the next page