6.10 Checking After Commissioning
Table 6-7
Table 6-7 Commissioning checklist
Check Item
No oil stain exists on the copper pipe thermal insulation
foam or bottom plate, or it has been cleaned.
The needle valve plug is secured (torque of 0.45±0.05
N·m), and valve bonnet is tightened.
The foreign matter inside the water pan and bottom plate
is cleaned up.
The air filter is correctly installed according to the air flow
direction on the frame.
Issue 13 (2023-08-20)
lists the commissioning checklist.
Copyright © Huawei Digital Power Technologies Co., Ltd.
6 Power-On Commissioning
Actual Result
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed
□ Passed □ Failed