NetCol5000-A050 In-row Air Cooled Smart Cooling
Product
User Manual
Figure 4-93 Connecting communications cables
If the length of a network cable in the FE teamwork is greater than or equal to
100 m, use the group-based ring networking mode.
1.
2.
3.
Figure 4-94 FE teamwork group-based ring networking (using 13 units as an
example)
----End
Issue 13 (2023-08-20)
NO TE
● Connect the COM/FE port on the main control module of the last unit in each group to
the RS485 port on the host.
● Customers can purchase the NetEco (an ECC is required) or a third-party NMS as the
monitoring system.
● If the number of units in a group is greater than 16, FE teamwork needs to be
implemented by group. For example, if the number of units under teamwork is 18, they
can be divided into two groups, for example, 9+9, 16+2, or 10+8.
Connecting units with odd numbers: Connect the FE_1 port of the unit with
an odd number to the FE_2 port of the unit with the next odd number.
Connecting units with even numbers: Connect the FE_2 port of the unit with
an even number to the FE_1 port of the unit with the next even number.
Connect FE_2 of No. 1 unit and FE_1 of No. 2 unit, and connect the remaining
FE_1 and FE_2 of the last two units.