Machine Installation; Machine Installation (Leveling) - Yamaha SIGMA-G5SII Service Information

Table of Contents

Advertisement

1.4.2. Machine Installation

1.4.2.1. Machine Installation (Leveling)

Note:
(a) Before setting up a jack or lever, remove the cutter guide
cover.
(b) The jacks shall be set in the two locations as shown in Fig.
A12.
(c) When the pallet jack is inserted in the front or rear direction,
use the jack with a width up to about 600mm. The machine
weight is about 1.8 tons.
(1) First, decide the machine installation position on the floor using a leveling string or
packing tape.
For the machine installation position, confirm it with the client before doing the
installation work.
(2) Move the machine to the installation position using the plumb bob, and align it with
the correct position.
(3) When the machine alignment is completed, install the machine temporarily with the
four height adjusters (leg type).
Machine Temporary Installation
(1.1) The standard for the machine temporary installation height shall be about
Note:
In the case that the machine is connected with an existing machine, the feed height in the existing
machine should be taken as the feed reference.
(Target value shall be 905mm from the floor to the component transfer surface)
84mm from the floor to the frame.
Fig. A13
Service Information
About 84 mm
SI1705004E-00=SIGMA-G5SII Service Manual
19/273
For Service Engineer
Jack set
Pallet Jack Width
up to about 600 mm
Fig. A12

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents