Optional) Connecting A Cable To The Asd Power Box Battery - Huawei FusionModule1000A20 Installation Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
Figure 6-33 Battery installation position
Step 2 Connect the battery cables to the reserved power cable terminals.
Figure 6-34 Connecting battery cables
----End
6.5.3 (Optional) Connecting a Cable to the ASD Power Box
Battery
Prerequisites
Issue 02 (2020-01-15)
Do not connect the red positive cable until power-on commissioning.
Ensure that battery cables for the extinguishant control panel are connected to correct
polarities.
The position of the ASD power box has been specified.
Documents delivered with the ASD power box have been obtained.
Copyright © Huawei Technologies Co., Ltd.
6 Installing Devices Inside the Pre-fab. Module
66