Huawei FusionModule1000A20 Maintenance Manual

Ct solution
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

Quick Links

FusionModule1000A20 CT Solution
V200R003C00
Maintenance Guide
Issue
01
Date
2019-02-25
HUAWEI TECHNOLOGIES CO., LTD.

Advertisement

Table of Contents
loading

Summary of Contents for Huawei FusionModule1000A20

  • Page 1 FusionModule1000A20 CT Solution V200R003C00 Maintenance Guide Issue Date 2019-02-25 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2 Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
  • Page 3: About This Document

    Indicates a potentially hazardous situation which, if not avoided, could result in serious injury or death. Indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 4 Change History Changes between document issues are cumulative. The latest document issue contains all updates made in previous issues. Issue 01 (2019-02-25) This issue is the first official release. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 5: Table Of Contents

    3.6.3 Monitoring System ................................39 3.6.4 Fire Extinguishing System (CE) ............................. 41 3.6.5 Other Systems .................................. 44 4 Alarms and Faults ........................ 46 4.1 TP48400B Alarms................................46 4.2 Alarms for the Cooling System ............................50 Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 6 5.3.9 Replacing a Water Sensor (Point Type) .......................... 88 5.3.10 Replacing Access Control Components ........................89 5.3.10.1 Replacing an IC Card Reader ............................ 89 5.3.10.2 Replacing an Exit Button ............................91 5.3.10.3 Replacing a Magnetic Lock ............................92 Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 7 5.4.1.10 Replacing the Extinguishant Control Panel (CE) ....................124 5.4.1.11 Replacing an Emergency Light (CE) ........................126 5.4.2 Replacing Batteries for the VESDA Power Box ......................128 6 FusionModule1000 Emergency Exit Guide ..............131 7 Acronyms and Abbreviations................... 132 Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 8: Operation And Maintenance Precautions

     Do not open batteries as electrolyte leakage may cause personal injuries. If you contact the electrolyte accidentally, immediately clean your skin with water and seek medical advice from a doctor. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 9 Take antistatic measures before removing the front panel from a VESDA; otherwise, the VESDA may be damaged.  During fire extinguishing system commissioning, disconnect the solenoid valve, and insert the fire cylinder safety pin to prevent agent release by mistake. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 10: Operation And Maintenance Preparations

    Prepare tools listed in Table 2-1 before performing O&M operations. Table 2-1 Tools Tools Phillips screwdriver Flat-head screwdriver Adjustable wrench Electrician's knife Needle-nose pliers Diagonal pliers Crimping tool Wire stripper RJ45 crimping tool Cable cutter Hex key Socket wrench Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 11: Obtaining Technical Documents

    ESD floor suction plate Vacuum cleaner The listed tools are for routine maintenance only. Prepare other tools as required. 2.2 Obtaining Technical Documents Table 2-2 lists the technical documents required for FusionModule1000 O&M. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 12 TP48400B-L20B1 V500R002 from http://e.huawei.com. User Manual ECC800 Data Center Describes how to use and Download this document Controller V100R001C30 maintain the ECC800. from User Manual http://support.huawei.com. Download this document from http://e.huawei.com. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 13 NetEco WebUI to obtain the NetEco version. If the NetEco version is iManager NetEco V600R007C80, see iManager NetEco Product Document - (V600R007C80) for details. Download this document from http://e.huawei.com. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 14: Container Entry Requirements

    Remove dust from tools and materials that need to be taken into the data center, and make a record.  Do not bring in forbidden items, such as storage devices, cameras, or portable hard disks into the FusionModule1000. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 15: O&M Personnel Skill Requirements

    With knowledge in the hardware and software of the container data center, system familiar with basic communications protocols, familiar with equipment interfaces in extra low voltage (ELV) systems, and proficient in operating the NetEco management system With ELV engineer qualifications Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 16 FusionModule1000 g system With fire engineer qualifications Lighting and Familiar with the overall configurations and layout of the structural FusionModule1000 system Experienced in maintaining the FusionModule1000 Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 17: Routine Maintenance

    No. cotton cloth, specified on it. painting gun (required for 2. For a few repainting a large smudges, area) scratches or Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 18 30 minutes before performing any further operation. LOGO and pattern Seek help from Huawei headquarters for a detailed painting damage solution. Frontline personnel can turn to local advertisement coating suppliers. 1. If a dent is less than 100 mm...
  • Page 19 Figure 3-2 Wiping a polished or damaged area using anhydrous alcohol Step 3 Paint one layer of zinc-rich primer on the damaged coat using a brush or painting gun, as shown in Figure 3-3. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 20 In the case that a container pattern has different colors, to prevent undamaged areas and those with different colors as the damaged area from being polluted during repainting, cover such areas using white paper and adhesive tape before repairing paint. Figure 3-4 Manual paint spray Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 21 3 (Use a colorimeter to measure the color difference. If a colorimeter is not available, check that no obvious edge exists between the repainted area and its surrounding.) The paint should also be free from bulges, scratches, flake-off, or cracks. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 22: Operating The Shutter In The Fire Extinguishing Compartment

    Step 2 Pull the rope at the side of the shutter in the fire extinguishing compartment to fold the shutter blades to one side. Then maintenance personnel can enter the fire extinguishing compartment to maintain the fire cylinder. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 23: Daily Maintenance

    Categ Mainten Operation Check Troubleshooting ance Standard Item Power TP48400 Check whether The door lock is Replace the door lock. Supply the door lock is intact and damaged. working Distrib properly. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 24 Check whether the SIM Alarms. messages can be card is properly installed. If received. the SIM card is faulty, replace it by following instructions in ECC800 Data Center Controller V100R001C30 User Manual. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 25: Monthly Maintenance

    SPD indicator is the SPD. For details, refer to 5.1.2.4 circuit breaker green. Replacing an SPD. status. The SPD Switch on the circuit breaker. circuit breaker is switched to Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 26: Cooling System

    Table 3-4 Monthly maintenance checklist for the cooling system Maintenance Item Operation Check Standard Troubleshooting 12.5 kW fresh air Air filter The filters are Clean the air filters. integrated unit blocked. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 27 Tighten or replace fan are not loose or screws. misshapen. The cable terminals Tighten the are securely connectors. connected. Compressor The anchor screws Tighten loose of the compressor screws. are tight. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 28 Check whether the Air vent air filters Replace by air vent air filters are are not blocked and following blocked. working properly. instructions in 5.2.3 Replacing an Air Vent Air Filter. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 29: Monitoring System

    Steady on: A fault Refer to ECC800 Data Center indicator alarm is generated. Controller V100R001C30 User Manual to handle alarms, or contact Off: No fault alarm Huawei technical support. is generated. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 30 0.5s (blinking at 10 Hz, on for 0.05s and then off for 0.05s) and then turns off for 0.5s. The cycle lasts for 10s. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 31 Power output Output voltage: For details, contact Huawei technical 90–240 V AC support. Steady on: The Check the input power cables. indicator power supply is normal. Off: No power supply is available. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 32 0.5s (blinking at 10 Hz, on for 0.05s and then off for 0.05s) and then turns off for 0.5s. The cycle lasts for 10s. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 33: Fire Extinguishing System (Ce)

    The power indicator Replace by following nt control on the turns on, and the instructions in 5.4.1.10 panel extinguishant alarm indicator Replacing the Extinguishant control panel. turns off. Control Panel (CE). Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 34 5.4.1.1 Replacing a Smoke Detector (CE). Heat Check the heat The indicator blinks Replace by following detector detector indicator. once every 6s. instructions in 5.4.1.2 Replacing a Heat Detector (CE). Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 35: Other Systems

    FusionModule 1000 are as follows:  Temperatur e: –20° C to +45° C  Relative humidity: 5%–95%  Solar radiation: ≤ 1120 W/m Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 36: Quarterly Maintenance

    TP48200B-L20B2 & load low TP48400B-N20B3 & voltage TP48400B-L20B1 V500R002 User disconnection Manual. (LLVD) voltage is inside the rated range. Check whether the The indicators indicators are in are normal. normal status. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 37: Monitoring System

    Steady on: A fault Refer to ECC800 Data Center indicator alarm is generated. Controller V100R001C30 User Manual to handle alarms, or contact Off: No fault alarm Huawei technical support. is generated. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 38 0.5s (blinking at 10 Hz, on for 0.05s and then off for 0.05s) and then turns off for 0.5s. The cycle lasts for 10s. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 39 Steady on: A fault Refer to ECC800 Data Center indicator alarm is generated. Controller V100R001C30 User Manual to handle alarms, or contact Off: No fault alarm Huawei technical support. is generated. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 40 0.5s (blinking at 10 Hz, on for 0.05s and then off for 0.05s) and then turns off for 0.5s. The cycle lasts for 10s. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 41 WiFi Steady on: The For details, contact Huawei technical indicator power input is support. normal but there is no data communication. Blinking: There is no data communication. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 42 ECC800 WebUI. replace the door status sensor by check the following instructions in 5.3.10.6 alarm Replacing a Door Status Sensor. information displayed on monitoring software terminal. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 43: Fire Extinguishing System (Ce)

    Repaint areas with paint flake-off or corrosion. flake-off, rust, rust by referring to 3.1 Container or corrosion. Repainting. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 44: Semi-Annual Maintenance

    TP48200B-L20B2 & load low TP48400B-N20B3 & voltage TP48400B-L20B1 V500R002 User disconnection Manual. (LLVD) voltage is inside the rated range. Check whether the The indicators indicators are in are normal. normal status. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 45: Cooling System

    If the superheat degree is too temperature large or too small, adjust it to of the pipe a proper value or contact wall on Huawei technical support. which the sensing bulb is mounted. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 46: Monitoring System

    Power output Output voltage: For details, contact Huawei technical 45–55 V DC support. Steady on: The Check the input power cables. indicator power supply is normal. Off: No power supply is available. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 47 5.3.9 (point type) water, and ECC800 WebUI. Replacing a Water Sensor (Point view alarms Type). in the management system. Hydrogen Check the The fan is clean. Clean the fan. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 48: Fire Extinguishing System (Ce)

    Replacing Fire Extinguishing commission following the displays related System Devices (CE). instructions in the alarms. Fire Extinguishing System Commissioning (CE) section in the commissioning guide for the solution in use. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 49 2. If the smoke density is above the alarm threshold, the indicator turns on. The extinguishant control panel generates an alarm and triggers the fire alarm bell. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 50 VESDA. working properly, and the VESDA and whether the restarts normally VESDA restarts after the mains power normally after the is disconnected. mains powered is disconnected. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 51: Other Systems

    Check cable Cables are Secure terminal connections, and connections. securely replace terminals that do not meet connected requirements. For details, see the without bare installation guide for the terminals. corresponding solution. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 52 (the cables works only a very short time under overload situations).  The bend radius of cables meets requirement  The cable armor is intact. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 53: Alarms And Faults

    If yes, check and rectify the temperature unit fault. 4. Remove the rectifier that generates the alarm and reinstall it after the indicator turns off. If the alarm still exists, replace the rectifier. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 54 3. Check whether the load disconnection disconnection voltage (44 V DC by default) is set too high voltage is set on the SMU. If yes, adjust it to a proper too high on value. the SMU. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 55 Poor contact 2. Remove the SMU and reinstall it to check of the SMU. whether the alarm is cleared. If the alarm  The SMU is still exists, replace the SMU. faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 56 5. Check whether the power system capacity is system insufficient for the loads due to rectifier voltage is set failures. If yes, replace the faulty rectifier. too low in manual mode.  Rectifiers are faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 57: Alarms For The Cooling System

    The control system Check the control is not working system operating properly. status. The heat load is Check the heat load higher than density in the expected. environment. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 58 Power alarm Major No power supply is Check the voltage. available or the input voltage is too low. The power cable is Check the power in poor contact. cable connection. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 59: Monitoring System Alarms

    Micro-Module Informati The network security Apply for a new network security certificate certificate is about to security certificate about to expire expire. promptly and change the existing one. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 60 2. Check the sensor cable connection. 3. The sensor is faulty. AI/DI_3 sensor 3. Replace the faulty failure sensor by following AI/DI_4 sensor instructions in ECC800 failure Data Center Controller AI/DI_5 sensor V100R001C30 User failure Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 61 2. The PSU cannot ECC800 Data Center AI/DI_2 low supply power properly. Controller V100R001C30 voltage alarm User Manual. AI/DI_3 low voltage alarm AI/DI_4 low voltage alarm AI/DI_5 low voltage alarm AI/DI_6 low voltage alarm Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 62: Access Actuator Alarms

    Check that IC card reader removed removed. is not removed. Account locked Informati The account fails to pass Check that the account the authentication for 10 fails to pass the times. authentication for 10 times. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 63: Smart Eth Gateway Alarms

    PoE1 output Major The first output is output is not overload overloaded or the first overloaded. power supply pin is short-circuited. 2. Check that the first power supply pin is not short-circuited. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 64: Ac Actuator Alarms

    The load is Check that the load is not short-circuited. short-circuited. Relay 1 Life Pre Warning The use duration for relay Contact Huawei technical Alarm 1 reaches the forewarning support. threshold. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 65: Wifi Converter Alarms

    Solution Severi 1. Check that the WiFi converter Communicatio Critica The network cable is network cable n Failure loose. indicator on the WiFi converter is normal. 2. Replace the network cable. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 66: Parts Replacement

    DC power system Rectifier TP48200B-N20B2 & (TP48400B) TP48200B-N20B3 & Monitoring module TP48200B-L20B2 & TP48400B-N20B3 & TP48400B-L20B1 V500R002 User Manual AC SPD Circuit breaker User interface board DC-DC converter panel Battery temperature sensor Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 67: Replacing Components For The Input Pdc

    Step 3 Remove the cables at the ATS top and label them, as shown by (1) in Figure 5-1. Step 4 Loosen the knob at the left of the ATS controller to remove the controller, as shown by (2) and (3) in Figure 5-1. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 68: Replacing An Mcb

    The PDC switch must be turned off. Ensure that the power input is disconnected during replacement. Impact on the System None Preparations Tools: electroprobe, insulation gloves, flat-head screwdriver, Phillips screwdriver, multimeter Materials: spare MCB Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 69: Replacing The Pd510 Electricity Meter

    A spare PD510 electricity meter of the same model is available and functional. If the condition allows, switch off the upstream circuit breaker of the PD510 electricity meter to be replaced. Impact on the System Certain services of the FusionModule1000 are interrupted. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 70: Replacing An Spd

    After power-on, press buttons on the PD510 panel, and check whether the LCD of the electricity meter displays information properly. ----End Follow-up Procedure Dispose of the removed PD510 electricity meter that is confirmed faulty. 5.1.2.4 Replacing an SPD Prerequisites Do not replace an SPD during a thunderstorm. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 71 SPD has no voltage before replacing the faulty SPD. Figure 5-2 shows how to detect the voltages. Figure 5-2 Detecting the voltages Step 4 Hold down the faulty SPD module and pull it out. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 72: Replacing An Indicator

    Impact on the System None Preparations Tools: Phillips screwdriver, multimeter Materials: spare indicator Documents: none Skill requirement: electrician's work permit Procedure Step 1 Switch off the protective miniature circuit breaker (MCB) or fuse. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 73: Replacing A Fuse

    A spare fuse of the same model is available and functional. When replacing a fuse, you must wear insulated gloves, and must not touch the input copper bar. Impact on the System None Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 74 Step 3 Reinstall the fuse terminal block in the PDC. Step 4 Check whether the new fuse works properly. ----End Follow-up Procedure Dispose of the removed fuse that is confirmed faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 75: Replacing An Ambient T/H Sensor

    Tools: pallet truck, wrench, protective gloves Materials: insulation tape, spare battery, copper bar or cable Documents: documents delivered with the DC power system battery, power supply and distribution system diagram, power supply and distribution device layout Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 76: Replacing A Light

    5.1.4 Replacing a Light Prerequisites Spare LED lights of the same model are available and functional. Impact on the System None Preparations Tools: multimeter Material: spare light Documents: none Skill requirement: electrician's work permit Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 77: Replacing The Power Pdb

    Step 1 Power off the power PDB based on the power supply and distribution system diagram. Step 2 Remove cables using a socket wrench and Phillips screwdriver. Step 3 Remove screws securing the power PDB and remove the power PDB. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 78: Replacing Cooling System Components

    Step 1 Turn off the power switch of the fresh air integrated unit. Step 2 After power-off, rotate the left and right lock holes on the front panel, and lift the panel to remove it. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 79: Replacing An Air Damper

    Step 2 Press the latch shown by (1) in Figure 5-6 to loosen the air damper. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 80: Optional) Replacing A Low-Temperature Component

    Tools: flat-head screwdriver Materials: spare low-temperature component Documents: cooling device installation position diagram Skill requirement: cooling engineer, common technician For the diagrams, see the initial configuration parameter manual for the solution in use. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 81: Replacing An Air Vent Air Filter

    Documents: none Skill requirement: cooling engineer Procedure Step 1 Remove the four M4 screw assemblies securing the meshed board using a Phillips screwdriver, and pull out the meshed board by the handle. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 82: Replacing A Hydrogen Exhaust Fan

    Material: quick-connect terminals, spare hydrogen exhaust fan Documents: power supply and distribution system diagram Skill requirement: extra low voltage (ELV) engineer For the diagrams, see the initial configuration parameter manual for the solution in use. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 83 Step 5 Remove the screws securing the hydrogen exhaust fan using a Phillips screwdriver. Figure 5-8 Removing the cover Step 6 Install the spare hydrogen exhaust fan, and tighten it using a Phillips screwdriver. Figure 5-9 Installing the hydrogen exhaust fan Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 84: Replacing Monitoring System Components

    Step 2 Label each cable and antenna based on the corresponding ports on the ECC800 main control module. Step 3 Remove the cables and antenna from the ECC800 main control module. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 85: Replacing An Ecc800 Psu (Ct)

    Step 3 Pull out ECC800 PSU from the subrack by the handle. Step 4 Place a spare ECC800 PSU in the subrack, push the locking latch leftwards to open the lock, and pull the handle outwards. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 86: Replacing An Ai/Di Module

    Materials: spare AI/DI module, insulation tape Documents: management system initial configuration table Skill requirement: extra low voltage (ELV) engineer For the table, see the initial configuration parameter manual for the solution in use. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 87: Replacing A Smart Eth Gateway

    5.3.4 Replacing a Smart ETH Gateway Prerequisites A spare ETH gateway of the same model is available and functional. Impact on the System Devices connected to the ETH gateway will be disconnected. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 88: Replacing A Camera

    For the table, see the initial configuration parameter manual for the solution in use. Procedure Step 1 Remove screws securing the transparent cover of the camera body using a Phillips screwdriver. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 89 Step 2 Use a Phillips screwdriver to remove the screws that fasten the camera to its base. Figure 5-13 Removing screws that secure the camera to its base Step 3 Remove the network cable and take out the camera. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 90: Replacing An External Camera

    Step 1 Remove the network cable connected to the external camera. Step 2 Remove the faulty camera using a Phillips screwdriver. Step 3 Install the new camera by following instructions in documents delivered with the external camera. ----End Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 91: Replacing A Signal Spd

    Step 1 Determine the position for installing the signal SPD based on the signal SPD installation position diagram. Step 2 Open the SPD box door of the external camera mounting kit, and remove the signal SPD clamping plate. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 92 Step 3 Remove cables connected to the faulty signal SPD, and remove the faulty signal SPD. Step 4 Install the spare signal SPD, and reconnect the cables in the same way. Step 5 Reinstall the signal SPD clamping plate. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 93: Replacing An Sd Card

    A spare SD card of the same model is available and functional. Impact on the System None Preparations Tools: camera screwdriver Materials: spare SD card Documents: monitoring device layout diagram Skill requirement: extra low voltage (ELV) engineer Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 94 Step 3 Insert a new SD card into the SD card slot. Figure 5-17 Installing an SD card Step 4 Reinstall the inner and front covers. ----End Follow-up Procedure Dispose of the removed SD card that is confirmed faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 95: Replacing A Water Sensor (Point Type)

    Figure 5-18 shows a point-type water sensor. Figure 5-18 Point-type water sensor Step 2 Remove the locking bolts of the water sensor using a Phillips screwdriver, and remove the water sensor, as shown in Figure 5-19. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 96: Replacing Access Control Components

    An IC card reader needs to be replaced.  A spare IC card reader of the same model is available and functional. Impact on the System None Preparations Tools: Phillips screwdriver, protective gloves Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 97 Step 4 Remove interconnection terminals from the IC card reader, and remove the IC card reader body. Step 5 Remove the two screws from the bottom of the new IC card reader, and remove the front cover. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 98: Replacing An Exit Button

    Material: spare exit button Documents: none Skill requirement: weak-current engineer Procedure Step 1 Disassemble the faulty exit button, remove cables, and remove the faulty exit button, as shown in Figure 5-22. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 99: Replacing A Magnetic Lock

    5.3.10.3 Replacing a Magnetic Lock Prerequisites  The magnetic lock needs to be replaced.  A spare magnetic lock of the same model is available and functional. Impact on the System None Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 100 Step 3 Use a 3 mm hex key to loosen screws from the baffle plate of the magnetic lock, as shown by (2) and (3) in Figure 5-23. Step 4 Replace the magnetic lock, and connect cables, as shown in Figure 5-24. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 101: Replacing An Emergency Door Release Button

    Tools: insulation tape, step ladder (2 m), Phillips screwdriver, protective gloves Material: spare emergency door release button Documents: none Skill requirement: weak-current engineer Procedure Step 1 Remove the emergency door release button. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 102 Remove the cover of the emergency door release button using a screwdriver, press the button, and rotate the door handle clockwise to open the container door. If the door can be opened, the emergency door release button is working properly. ----End Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 103: Replacing An Access Actuator

    5.3.10.6 Replacing a Door Status Sensor Prerequisites  The door status sensor needs to be replaced.  A spare differential door status sensor of the same model is available and functional. Impact on the System None Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 104 Open the door and check whether the management system reports an alarm indicating that the door was opened. If yes, the door status sensor is working properly. ----End Follow-up Procedure Dispose of the removed door status sensor that is confirmed faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 105: Optional) Replacing A T/H Sensor

    Step 3 Reset parameters by referring to the management system initial configuration guide. Step 4 Check that the new T/H sensor is working properly. If the T/H sensor displays the temperature and humidity properly after power-on, the T/H sensor is working properly. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 106: Replacing An Ac Actuator

    ----End Follow-up Procedure Dispose of the removed AC actuator that is confirmed faulty. 5.3.13 Replacing a WiFi Converter Prerequisites A spare WiFi converter of the same model is available and functional. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 107: Replacing A Pad

    A spare pad of the same model is available and functional. Impact on the System None Preparations Tools: ESD wrist strap, ESD gloves, label, marker Materials: new pad of the same model Documents: none Skill requirement: extra low voltage (ELV) engineer Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 108: Optional) Replacing A Cim

    If the CIM is not damaged, hold down the networking switch for the CIM to clear the current network (including the network parameters for all the BIMs managed by the CIM). Step 2 Remove and label CIM cables. Step 3 Remove the CIM from the fastener. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 109: Removing A Camera Spd Module

    An SPD module consists of an SLPU and a UFLP. The SLPU is a 19-inch wide and 1 U high box-type device. Figure 5-30 shows the SLPU, and Figure 5-31 shows the UFLP panel. Figure 5-30 SLPU appearance Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 110 Step 6 Connect the network cable inside the pre-fab. module and the network cable of the peer device outside the pre-fab. module to the corresponding ports on the UFLP. ----End Follow-up Procedure Dispose of the removed camera SPD module that is confirmed faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 111: Replacing Fire Extinguishing System Components

    2ND STAGE NO terminal on the extinguishant control panel to enable the linkage control function, and inform the administrative departments that the system has become operational. Figure 5-32 Position of the 2ND STAGE NO terminal Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 112: Replacing A Heat Detector (Ce)

    Follow-up Procedure Dispose of the removed smoke detector that is confirmed faulty. 5.4.1.2 Replacing a Heat Detector (CE) Prerequisites A spare heat detector of the same model is available and functional. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 113 Step 1 Disconnect the battery cables, and switch off the input circuit breaker of the extinguishant control panel. Step 2 Hold the heat detector, and rotate it counterclockwise to remove it from the base. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 114: Replacing Warning Signs (Ce)

    5.4.1.3 Replacing Warning Signs (CE) Prerequisites A spare warning sign indicator of the same model is available and functional. Impact on the System The fire extinguishing system stops working during the replacement. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 115 Step 1 Disconnect the battery cables, and switch off the input circuit breaker of the extinguishant control panel. Step 2 Loosen the screws securing the warning sign and its base using a Phillips screwdriver, and remove the cover of the warning sign. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 116: Replacing An Internal Horn Strobe (Ce)

    A spare horn strobe of the same model is available and functional. Impact on the System The fire extinguishing system stops working during the replacement. Preparations Tools: Phillips screwdriver, step ladder Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 117 Step 1 Disconnect the battery cables, and switch off the input circuit breaker of the extinguishant control panel. Step 2 Remove screws from the horn strobe cover using a Phillips screwdriver, and remove the cover. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 118 Step 5 Install the new horn strobe in the same way, connect the cables, and install the cover. Step 6 Switch on the input circuit breaker of the extinguishant control panel, and connect the battery cables. Step 7 Check that the new horn strobe is working properly. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 119: Replacing An External Horn Strobe (Ce)

    The fire extinguishing system stops working during the replacement. Preparations Tools: Phillips screwdriver, step ladder Materials: spare horn strobe, key to the control box Document: fire extinguishing device layout diagram (CE) Skill requirement: fire engineer Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 120 Step 2 Remove screws from the horn strobe using a Phillips screwdriver, and remove the cover. Figure 5-42 Removing the cover Step 3 Remove the cables to the horn strobe. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 121 Flip the key to Enable Control counterclockwise (rightward). Reset the extinguishant control panel by pressing Reset on it. Then, reset key to Enable Control clockwise (leftward). ----End Follow-up Procedure Dispose of the removed horn strobe that is confirmed faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 122: Replacing A Fire Alarm Bell (Ce)

    Figure 5-44 Position of the 2ND STAGE NO terminal Procedure Step 1 Disconnect the battery cables, and switch off the input circuit breaker of the extinguishant control panel. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 123 If the alarm bell starts and aborts normally, and rings loud and clear when it is started, the alarm bell is working properly. Reset the key to Enable Control by flipping it leftward. ----End Follow-up Procedure Dispose of the removed fire alarm bell that is confirmed faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 124: Replacing The Extinguishant Abort Button (Ce)

    Figure 5-46 Position of the 2ND STAGE NO terminal Procedure Step 1 Disconnect the battery cables, and switch off the input circuit breaker of the extinguishant control panel. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 125 Step 4 Remove the screws on the extinguishant abort button base using a Phillips screwdriver, and remove the base. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 126 Disconnect the wiring terminals from the electrical actuator on the fire cylinder. After the wiring terminals are disconnected from the electrical actuator, the extinguishant control panel generates an alarm, which is normal. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 127: Replacing Batteries For The Extinguishant Control Panel (Ce)

    Step 2 Remove the extinguishant control panel batteries. Step 3 Install the spare batteries to the proper position of the extinguishant control panel. Step 4 Connect battery cables to the extinguishant control panel in the same way. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 128: Replacing A Fire Cylinder (Ce)

    The fire extinguishing system stops working during the replacement. Preparations Tools: pipe wrench, pallet truck, Phillips screwdriver, adjustable wrench, protective gloves Materials: spare fire cylinder, sealing tape Document: fire extinguishing device layout diagram (CE) Skill requirement: fire engineer Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 129 Remove the I-shaped connection pipe. Remove the threaded adapter from the container valve of the fire cylinder. Step 5 Remove the pneumatic switch hose from the container valve of the fire cylinder. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 130 Connect the threaded adapter to the fire cylinder. Connect the I-shaped connection pipe to the threaded adapter. Connect the high-pressure hose. Step 11 Reinstall the electrical actuator to the container valve of the fire cylinder. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 131: Replacing The Extinguishant Control Panel (Ce)

    5.4.1.10 Replacing the Extinguishant Control Panel (CE) Prerequisites A spare extinguishant control panel of the same model is available and functional. Impact on the System The fire extinguishing system stops working during the replacement. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 132 While removing the cables, label the cables with their corresponding port numbers for later connection. Step 4 Remove the corrugated pipes and cables from the extinguishant box. Step 5 Remove the screws using a Phillips screwdriver, and take out the faulty extinguishant control panel. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 133: Replacing An Emergency Light (Ce)

    5.4.1.11 Replacing an Emergency Light (CE) Prerequisites A spare emergency light of the same model is available and functional. Impact on the System None Preparations Tools: Phillips screwdriver, flat-head screwdriver, step ladder, protective gloves Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 134 Step 5 Install the new emergency light base and the panel in the same way. Step 6 Remove the red pin, and reinstall the protective cover. Figure 5-58 Position of the red pin Step 7 Reconnect the power plug of the emergency light. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 135: Replacing Batteries For The Vesda Power Box

    Step 1 Move the VESDA power box batteries to the installation position indicated on the fire extinguishing device layout diagram. Step 2 Switch off the standby power supply for the VESDA. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 136 Step 5 Replace the batteries, and connect battery cables. Distinguish the positive and negative battery terminals when connecting battery cables. Figure 5-60 Connecting battery cables Step 6 Reinstall the battery protective panel. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 137 Turn on the standby power switch. If the power fault indicator is off, the batteries are working properly. ----End Follow-up Procedure Dispose of the removed VESDA power box batteries that are confirmed faulty. Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 138: Fusionmodule1000 Emergency Exit Guide

    If an emergency occurs, push open the nearest pre-fab. module door shown in the emergency exit diagram with force, as shown in Figure 6-1. Then exit from the pre-fab. module immediately. Figure 6-1 Opening the emergency exit door Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 139: Acronyms And Abbreviations

    Alternating Current automatic transfer switch control area network Conformite Europende digital distribution frame energy control center liquid crystal display monitor display module power over Ethernet power distribution cabinet power distribution unit Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.
  • Page 140 FusionModule1000A20 CT Solution Maintenance Guide 7 Acronyms and Abbreviations rPDU rack power distribution unit subscriber identity module uninterruptible power system video cloud node VESDA very early smoke detection apparatus Issue 01 (2019-02-25) Copyright © Huawei Technologies Co., Ltd.

Table of Contents