5.2 (Optional) Installing Awnings

Prerequisites
Context
An awning must be installed on the top of the main entrance door to prevent rainwater from
entering the pre-fab. module when the door is open.
Preparations
Tools: socket wrench, Phillips screwdriver, glue gun, step ladder
Materials: awning, awning mounting plate, rubber pad, white sealant, awning bolt
Skill requirement: common technician
Procedure
Step 1 Remove the eave.
Issue 02 (2020-01-15)
The pre-fab. modules have been installed.
The position for installing the awning has been specified.
Store the removed screws for securing the awning mounting plate.