FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
Figure A-5 DPJ end connector
(1) Body
(3) Guarding
(5) Plastic-coated metal hose
Preparations
Tools: small cutter, scissors, wrench dedicated for feeder windows, glue gun
Material: sealant
Documents: none
Skill requirement: skilled technician
Procedure
Step 1 Cut the plastic-coated metal hose to facilitate connection between the metal hose and the
ferrule.
1.
2.
Step 2 Remove the sealant from the DPJ end connector.
Issue 02 (2020-01-15)
Use a small cutter or a pair of scissors to cut the hose at the joint between the
plastic-coated metal hose and the end connector at an angle of 30 to 45 degrees, as
shown in
Figure
A-6.
Figure A-6 Cutting a hose
Trim any burrs on the cut.