Huawei FusionModule1000A20 Installation Manual page 98

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
Figure A-10 Disassembling a waterproof metal connector
Step 2 Route a cable into the pre-fab. module through the waterproof metal connector, as shown in
Figure
People inside and outside the pre-fab. module should work together to route the armored
power cable to the specified connection position inside the pre-fab. module.
To facilitate operation during internal routing, you can remove some top plate in the
pre-fab. module aisle.
Figure A-11 Routing cables
Step 3 Wrap four circles of waterproof sealing tape around the joint between the cable and the
waterproof metal connector, as shown in
Figure A-12 Wrapping sealing tape
Issue 02 (2020-01-15)