SmartLogger2000-(10-C, 11-C)
User Manual
5.2 System Power-On
Prerequisites
You have performed the operations described in
Context
In a scenario with a smart array controller, the SmartLogger is installed before delivery, and
the power cable is connected.
Procedure
Step 1 Insert the output terminal of the power adapter into the 12V IN port of the SmartLogger.
Step 2 Insert the power cable into the power adapter.
Step 3 Insert the power cable plug into an AC socket.
In a scenario without a smart array controller, place the power adapter on the top of the
SmartLogger and secure the power adapter using cable ties.
Figure 5-1 Connecting the power cable in a scenario without a smart array controller
Step 4 Switch on the circuit breaker of the AC socket.
Step 5 Switch on the upstream circuit breaker of the AC power cable.
----End
Issue Draft A (2017-02-15)
When powering on the system, use the power adapter delivered with the product. The
rated input of the power adapter is 100–240 V AC, and 50 Hz or 60 Hz. If adapters of
other models are used, the equipment may be damaged.
Select an AC socket that matches the power adapter.
Step 5
needs to be performed in the PLC networking scenario.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5.1 Checking Before
Power-On.
5 System Operation
64