Figure 8-2 Reactive power control

8.2 Application Scenarios

8.2.1 Local Scheduling

Local scheduling applies to a PV plant with the rated power no greater than 100 kW and less
than five grid-tied SUN2000s. Because the power system is small, power grid companies have
low requirements on power adjustment, which can be achieved by local control.
Some power grid companies do not require remote reactive power control for a PV plant, but
require local reactive power adjustment in various modes.
Users can set the control mode over the WebUI based on the actual output characteristics of
each PV plant. The SmartLogger can continuously control power output of SUN2000s
according to user configurations.
Issue Draft A (2017-02-15)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 Power Grid Scheduling
165

Advertisement

Table of Contents
loading

This manual is also suitable for:

Smartlogger 2011-cSmartlogger2010-c

Table of Contents