NetCol8000-C(070, 130, 190) In-room Chilled Water
Smart Cooling Product
User Manual
Table 3-4 Tools for electrical connections and tests
Appearance, Specifications, and Name
Clamp meter
3.1.3 Material Preparations
Materials are classified to Huawei-provided, self-purchased, and onsite prepared
materials, which are marked as mandatory, optional, and engineering purchasing
in this document.
●
●
●
3.1.3.1 Water Inlet Pipe of the Wet Film Humidifier
Figure 3-4 Connecting a water inlet pipe
(1) External thread connector: G 1/2 in.
(reserved device port)
(3) Pipe: matches the conversion adapter
(engineering procurement).
3.1.3.2 Drainpipe
Issue 02 (2020-08-30)
Mandatory: materials that are provided by Huawei and can be found in the
delivered fittings.
Optional: materials that can be purchased from Huawei or any other vendor
(if you have ordered the materials from Huawei, you do not need to purchase
them elsewhere). For details about the specifications of such materials to be
purchased, see the following sections.
Engineering procurement: materials that are not configured by Huawei and
need to be purchased from another vendor.
Copyright © Huawei Technologies Co., Ltd.
Insulation gloves
(2) Rigid pipe conversion adapter: G 1/2 in.,
connected to a rigid pipe with inner screw
threads (engineering procurement)
3 Installation Guide
31