ECC800 Data Center Controller
User Manual (for ECC800-Pro)
Procedure
Step 1 Log in to the ECC800-Pro WebUI as an administrator.
Step 2 Open skylights.
Table 8-55 Opening skylights
Path
Monitoring > Aisle >
Skylight Actuator Group >
Skylight Actuator n >
Controls
● Remotely opening the skylight may open the smart module skylight, and this
● When a smart module actuator is configured, you need to set parameters for
----End
Example
The following figure shows how to open the skylights controlled by skylight
actuator 1.
Figure 8-39 Opening skylights
Follow-up Procedure
After the maintenance is complete, O&M personnel need to close the skylights in
the smart module manually.
Issue 02 (2020-09-07)
CA UTION
may pose security risks. Exercise caution when performing this operation.
the smart module actuator. The setting process is similar.
Copyright © Huawei Technologies Co., Ltd.
Setting
Select Remote open scuttle and click Submit