4.1 Installation Preparations

4.1.1 Installation Environment

Before installing the UPS, note the following:

4.1.2 Installation Clearances

For details about the clearance requirements for installing a cabinet, see the
corresponding FusionPower6000 user manual.

4.1.3 Tools

The onsite operation personnel can select tools based on the site requirements.
Issue 02 (2024-01-05)
Do not install the UPS in a high-temperature, low-temperature, or damp place
that is beyond the technical specifications.
Install the UPS far away from water sources, heat sources, and inflammable
and explosive materials. Keep the UPS free from direct sunlight, dust, volatile
gases, corrosive materials, and salty air.
Do not install the UPS in environments with conductive metal scraps in the
air.
The optimal operating temperatures for valve-regulated lead-acid (VRLA)
batteries are 20–30°C. Operating temperatures higher than 30°C shorten the
battery lifespan, and operating temperatures lower than 20°C reduce the
battery backup time.
Ensure that the floor or installation support can bear the weight of the UPS,
batteries, and battery racks.
If the UPS is equipped with a top outlet kit, do not install devices that are
easy to swing on the top of the UPS. Otherwise, the devices may fall off.
Copyright © Huawei Digital Power Technologies Co., Ltd.
4

Installation

4 Installation
60

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusionpower6000 ups5000-h-600 kva-ftm

Table of Contents