Commissioning
6.7 Commissioning: Basic procedure
● "Remaining time until test stop"
This indicates the remaining time until dynamic operation and test of the safety switch-off
signal paths are performed (p9660).
● "Shutdown paths require testing"
Select the parameters to be interconnected with the status "Shutdown path test required"
(r9773.31). One or more interconnections are possible, but not mandatory.
● Click "Close" to return to the "Safety Integrated" dialog box.
Safe s top functions (SS1, SS2, SOS, SAM)
● Click "Safe stop functions (SS1, SS2, SOS, SAM)" in the "Safety Integrated" dialog box to
parameterize SS1, SS2, SOS, and SAM:
● Change to the "SS1" page.
– "Delay time STOP F -> STOP B"
– "Delay time SS1/STOP B -> STO active"
– "Shutdown velocity/shutdown speed"
– "SS1 monitoring"
256
Enter a value for the delay time here for the transition from STOP F to STOP B
(p9555).
Enter a value for the delay time here for the transition from the safe pulse suppression
to STOP B (p9556).
Enter a value for the shutdown speed SS1 (p9560).
You can select whether you want to use SS1 with OFF3 or with external stop (p9507)
here.
Function Manual, (FHS), 07/2016, 6SL3097-4AR00-0BP6
Safety Integrated