FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Step 2 (Optional) Commission the ATS.
1.
2.
Step 3 Switch on the SPD circuit breaker in the PDF to power on the SPD. The SPD
indicator becomes steady green.
Step 4 (Optional) Commission the PD510 electricity meter.
1.
2.
Step 5 Switch on the output circuit breakers in the PDF level by level as required to
supply power to downstream equipment.
----End

9.1.1.1 (Optional) Commissioning the ABB ATS

Context
Perform system commissioning and power-on strictly according to the system
manual and ATS instructions. For any changes in operations and parameters,
consult Huawei engineers. Otherwise, system commissioning or power-on may
fail, or even the cabinet is damaged.
Procedure
Step 1 Switch on all SPD circuit breakers in the integrated UPS.
Step 2 Switch on the upstream power input circuit breaker for the integrated UPS to
power on the UPS cabinet. If the Power indicator in the upper part of the
integrated UPS lights up, the UPS cabinet is powered on properly.
Step 3 Turn on the circuit breakers of the ATS operation mechanism (Q1 and Q2 in the
left lower part at the rear of the cabinet) to power on the ATS operation
mechanism.
Step 4 Check whether the controller has alarms. If an alarm exists, rectify the fault first.
Step 5 Press the locking latch on the ATS panel, pull out the handle, and insert it into the
slot.
Step 6 Check the ATS Motor/Manual selection lever, and flip it to the Motor mode.
Step 7 Check the AC input and configuration status of the ATS.
After the AC input is normal, the ATS controller starts. Check and set ATS
parameters based on the AC input parameters.
Issue 03 (2022-12-15)
(Optional) If an 8D ATS is configured, go to
Commissioning the ABB ATS
After the ATS is commissioned, go to
For details about how to commission the PD510 electricity meter, see
Commissioning the PD510 Electricity
After ensuring that the PD510 electricity meter works properly, go to
CA UTION
Copyright © Huawei Digital Power Technologies Co., Ltd.
9 Commissioning Core Components
9.1.1.1 (Optional)
to perform the commissioning.
Step
3.
Meter.
9.1.1.2
Step
5.
57

Advertisement

Table of Contents
loading

Table of Contents