Preparing For The Cooling System Power-On Commissioning - Huawei FusionModule1000A20 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Procedure
Step 1 Understand the layout of the power supply and distribution devices by referring to
the power supply and distribution device layout diagram.
Step 2 Understand the control relationship of the power supply and distribution system
by referring to the power supply and distribution system diagram.
Step 3 Understand the power-on commissioning process by referring to the general
power-on commissioning process.
Step 4 Understand the initial configurations of the power supply and distribution system
by referring to the power supply and distribution device initial configuration table.
----End
4.5 Preparing for the Cooling System Power-On
Commissioning
Prerequisites
The transport protection fasteners have been removed in the 16 kW scenario, or
the compressor transportation fasteners have been removed in the 24 kW
scenario.
Preparations
Tools: multimeter, Phillips screwdriver
Documents: cooling device layout diagram, cooling device initial configuration
table
Skill requirement: cooling engineer
Procedure
Step 1 Understand the layout of cooling devices by referring to the cooling device layout
diagram.
Step 2 Understand the initial configurations of the cooling system by referring to the
cooling device initial configuration table.
Step 3 Verify that the condensate drainpipe is not blocked.
Step 4 Verify that there is no leakage point in the door, floor, or ceiling of the
FusionModule1000.
----End
Issue 03 (2022-12-15)
NO TE
For the diagrams and tables, see the initial configuration parameter manual for the solution
in use.