FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
3.
Step 2 Commission the NetEco management system.
1.
2.
3.
----End
7.4 Fire Extinguishing System Commissioning (CE)
Prerequisites
●
●
● Before commissioning the fire extinguishing system, remove the electrical
actuator from the container valve of the fire extinguisher cylinder. This prevents
the extinguishant release due to misoperations, and prevents accidental
damage during the commissioning. After the commissioning of the fire
extinguishing system, reinstall the container valve to the electrical actuator.
● To avoid damage to the heat detector, keep a proper distance between the
heating device and the heat detector during the commissioning.
Preparations
Tools: multimeter, smoke pistol, heating device, flat-head screwdriver, Phillips
screwdriver, step ladder
Issue 03 (2022-12-15)
NO TICE
Verify that all devices in the initial configuration table communicate with the
management system properly.
Check that the views in the management system are consistent with the
running status of the data center. If any inconsistency is found, contact
Huawei technical support.
Enter the initial user name and password on the NetEco WebUI to log in to
the management system.
Check the connections of all monitoring devices by referring to the monitoring
device layout diagram.
NO TICE
Verify that all devices in the initial configuration table communicate with the
management system properly.
Check that the views and videos in the management system are consistent
with the running status of the data center. If any inconsistency is found,
contact Huawei technical support.
The extinguishant control panel has been powered on.
The management system is working properly.
D ANGER