6.1 Power-on Commissioning

Prerequisites
● Prepare a flashlight before powering on the lighting system.
● Circuit breakers of various specifications are reserved in the power supply
system. If any of these circuit breakers are used, conduct proper operations on
them for the commissioning.
Preparations
Tools: none
Document required: initial configuration parameter manual
Skill requirement: power distribution engineer
Procedure
Step 1 Switch on the external input circuit breaker.
Step 2 Switch on the power supply circuit breaker by referring to the power supply and
distribution system diagram, and power on the FusionModule1000 level by level.
Issue 03 (2022-12-15)
6
You have prepared for the power-on commissioning.
You have verified all the specifications for the power-on.
You have put on protective articles.
NO TICE
NO TE
For equipment with dual power inputs, circuit breakers of both power inputs must be
switched on.
Copyright © Huawei Digital Power Technologies Co., Ltd.