FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Prerequisites
The FusionModule1000 has passed the power-on commissioning and is working
properly.
Preparations
Tool: point thermometer
Documents: cooling device layout diagram, cooling device initial configuration
table, documents delivered with the smart cooling product
Skill requirement: cooling engineer
Procedure
Step 1 Set the cooling threshold temperature by referring to the documents delivered
with the smart cooling product, and check whether the smart cooling products
respond accordingly, for example, the fan speed increases or decreases. After the
cooling system of the smart cooling product starts, inspect the cooling effect by
testing the entire system power under corresponding working conditions.
Step 2 Use a point thermometer or thermocouple to measure the ambient temperature.
Step 3 Change the temperature setting back to the initial setting specified in the cooling
device initial configuration table.
----End
7.3 The Management System Commissioning
Before putting the FusionModule1000 into use, you must commission the
management system to ensure normal running.
7.3.1 Preparing for Commissioning the Management System
Tool Preparations
Multimeter, network cable tester, and RJ45 crimping tool
(Optional) Preparations for Modifying the Management System Initial
Configurations
Issue 03 (2022-12-15)
NO TE
For the diagrams and tables, see the initial configuration parameter manual for the solution
in use.
NO TE
Use a point thermometer or thermocouple to measure the temperature near the return air
vent of the smart cooling product and compare the temperature with the return air
temperature displayed on the LCD. If the values differ by less than 1°C, the smart cooling
product is working properly.