Commissioning The Asd - Huawei FusionModule1000A20 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One
Data Center
Commissioning Guide
Figure 9-30 Red button of the emergency light
(1) Red button of the emergency light
----End

9.4.2 Commissioning the ASD

Preparations
Tool: smoke pistol
Documents: documents delivered with the ASD, fire extinguishing device layout
diagram, power supply and distribution system diagram
Skill requirement: fire engineer
Procedure
Step 1 Switch on the input power circuit breaker for the ASD power box for the protected
area and connect the ASD battery based on the power supply and distribution
system diagram.
Step 2 (Optional) Perform power-on commissioning by following instructions in
documents delivered with the ASD.
Step 3 Release smoke in the protected area using the smoke pistol. Verify that the ASD
alarm indicator lights up, and that an alarm is generated in the management
system.
Issue 03 (2022-12-15)
NO TE
● The red button is located at one side of the emergency light.
● If the result expected for each step appears, the emergency light is working properly.
NO TE
For the diagrams, see the initial configuration parameter manual for the solution in use.
NO TE
The ASD is commissioned before delivery. A ASD that is newly installed or used as a
replacement must be commissioned as instructed by the delivered documents.
Copyright © Huawei Digital Power Technologies Co., Ltd.