5.2.3 Commissioning Procedure

Prerequisites
Check that the smart cooling product is properly powered on.
Before starting the compressor after power-on, ensure that the electric heating
belt of the crankcase has been preheated for more than 12 hours.
Context
High-quality refrigerant R410A is recommended.
Wear antifreeze gloves when performing refrigerant related operations.
The following are the tools used for commissioning and refrigerant charging:
Issue 02 (2021-06-30)
On the Running Parameters tab page, set smart cooling product running
parameters.
NO TE
On the Running Parameters tab page, you are advised to set Temperature setpoint
to 23°C, Humidity setpoint to 50% RH, Control mode to Cold aisle average value
control, and Cold aisle T/H sensor fault enable and Hot aisle T/H sensor fault
enable to Enable.
On the Controls tab page, set the smart cooling product control parameters
(such as on/off control parameters).
CA UTION
After the smart cooling product is shut down, the temperature of the smart
module increases and data running is affected. Exercise caution when
performing this operation.
NO TICE
CA UTION
Charging tools: pressure gauge (measuring range ≥ 4.0 MPa), rubber hose
(withstand pressure ≥ 4.5 MPa), vacuum pump
Measurement tool: electronic balance
Protective tools: insulation gloves, antifreeze gloves, and insulation shoes.
Other tools: flashlight