Cisco ONS 15454 Manual page 41

Turning up a node
Hide thumbs Also See for ONS 15454:
Table of Contents

Advertisement

Turning Up a Node
DLP-G356 Installing Fiber-Optic Cables from the 32WSS/32DMX and 32MUX-O/32DMX-O Cards to the Deep Patch Panel Tray
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
The following node types require the following
equipment. The cards and patch panels should already
be installed before you begin this procedure.
For terminal nodes, one of the following card sets:
• One 32MUX-O card and one 32DMX-O or
32DMX card
• One 32WSS card and one 32DMX or 32DMX-O
card
• One 32WSS-L cards and one 32DMX-L card
Plus one deep patch panel tray, preinstalled with MPO
cables (each MPO cable is terminated on one end with
one MPO connector and on the other end with eight
LC-type connectors)
For hub nodes, one of the following card sets:
• Two 32MUX-O cards and two 32DMX-O or
32DMX cards
• Two 32WSS cards and two 32DMX or
32DMX-O cards
• Two 32WSS-L cards and two 32DMX-L cards
Plus two deep patch panel trays, preinstalled with
MPO cables (each MPO cable is terminated on one
end with one MPO connector and on the other end
with eight LC-type connectors)
For ROADM nodes, one of the following card sets:
• Two 32WSS cards and two 32DMX or
32DMX-O cards
• Two 32WSS-L cards and two 32DMX-L cards
Plus two deep patch panel trays, preinstalled with
MPO cables (each MPO cable is terminated on one
end with one MPO connector and on the other end
with eight LC-type connectors)
NTP-G34 Installing Fiber-Optic Cables on DWDM
Cards and DCUs, on page 27
As needed
Onsite
None
Turning Up a Node
41