Installing the SVI II ESD Display Cover
The replacement Display Cover is shipped with a lanyard to prevent the cable (that connects
from the display to the Terminal Board) from breaking. Insert the lanyard under the screw in
the lower left corner that attaches the terminal board to the SVI II ESD housing.
To install the cover:
1. Install the lanyard and tighten the screw to 5 in/lb.
2. Using a 3mm hex key, remove the screw from the lower left corner, connecting the
terminal board to the SVI II ESD housing.
3. Connect the cable from the display into the LCD connector on the terminal board.
4. Ensure that the gasket is in its groove in the housing.
5. Place the cover over the screw mounts.
6. Tighten the four screws with the 5 mm hex key.
7. After installing the new display "Powering Up the SVI II ESD" on page 78
Ensure that:
1. The gasket is seated in the groove in the housing flange.
2. No wires or retaining cable can be trapped under the cover flange.
3. The flange area is not corroded and the surface is not scarred.
4. The four cover bolts are securely tightened to 50 in/lb.
86 |
=GE Oil & Gas
The cover of the SVI II ESD is a critical component for safety in
NOTE
Hazardous Areas. To ensure safe operation the flat surfaces of the
cover and the housing must be clean and absolutely free of
particles or dents. There must be no gap between the housing and
cover; torque spec is 50 in/lb.
© 2016 General Electric Company. All rights reserved.