Initial Startup; Factory Configuration; Getting Started; Verify Installation - Honeywell Vertex M Technical Handbook

Continuous gas monitor
Hide thumbs Also See for Vertex M:
Table of Contents

Advertisement

Vertex M
24-Point Continuous Monitor
TM
3.1 Startup
This section describes the Vertex M System startup
sequence.

3.1.1 Initial Startup

Use this section to turn on your Vertex M System and to
configure the analyzer modules for specific gas locations.
There are six parts to this startup procedure:

3.3 Verify Installation

3.4 Power Up

3.5 Start Program
3.6 Configuration Utility
3.7 Load Tape
3.8 Leak Checking Sample Lines
3.9 Verify Flow Rates and Supply Vacuum

3.1.2 Factory Configuration

Honeywell Analytics loads all software on the DAq at
the factory. The Universal Chemcassette
configured for the mineral acid family of gases and the
Pyrolyzer Analyzers for NF
each point for the target gases at your facility.

3.2 Getting Started

Before startup and configuration, gather the following
information:
The location to which each point is connected
Target gas at each location
Alarm levels
Relay configuration
3.3 Verify Installation
Ahead of the startup sequence, make sure that the
following installation steps have been completed:
Section 3 - Startup
Analyzers are
®
. You will need to configure
3
Sample lines
Exhaust line
AC power connection
Relay wiring
See
Section 2 Installation
3.4 Power Up
Use the rack power switch behind the front door to
power up the Vertex M System.
1. Open front door.
2. Turn on rack power switch.
3. Turn on power switch to appropriate analyzers.
4. Close and latch front door.
After 15 seconds, the analyzer status LEDs sequence
four times through all colors.
Analyzer / Pyrolyzer
Power Switches and Indicators
Rack Power Switch
3-2
for connection details.

Advertisement

Table of Contents
loading

Table of Contents