Commissioning

9.3 Series commissioning

9.3
Series commissioning
The setting for the safety monitoring functions is automatically transferred with
other data in the course of a normal series commissioning process. The following
steps need to be taken in addition to the normal commissioning procedure:
1. Enter a user agreement
2. Carry out the acceptance test
Sequence of operations for series commissioning
The following sequence of operations is recommended when commissioning series
equipment:
S Download the data set for the series machine into the control.
S Adjust the absolute encoder.
S Carry out a POWER ON.
This ensures that any errors -- i.e. deviations in the data content that may exist
between the NCK and drive -- will be detected by the checksum check and
crosswise data comparison.
Data must be checked if an error is detected. Cross check errors on the hard-
ware--related cross checksums (Alarm 27035, message F01680 with ID 2) or
Alarm 27032 are normal if the series commissioning data come from another
machine. These errors can be removed using the "Confirm SI--HW" softkey
(see Chapter 9.6 "Motor replacement or encoder replacement").
If an error no longer occurs, then data has not been changed and is identical
to the acceptance test data. The copy function may be used if data is sub-
sequently altered.
S Carry out random function tests.
The tests are required for acceptance of the new machine.
Software/hardware upgrade
Warning
!
Please carefully read the instructions in the relevant Update Manual before
updating the software.
9-568
SINUMERIK 840D sl/SINAMICS S120 SINUMERIK Safety Integrated (FBSI sl) - - 10.2015 Edition
© Siemens AG 2015 All Rights Reserved
10/15

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics s120

Table of Contents