Step 10 (Optional) Check whether the fire alarm signals are reported to the management
system.
Step 11 Reinstall the electrical actuator on the container valve.
----End

5.4 System Power-Off

Prerequisites
The FusionDC1000 is powered on, commissioned, and working properly.
Issue 01 (2021-04-20)
Figure 5-16 Extinguishant Released indicator on
Reset the extinguishant control panel.
NO TE
Wait for one minute and turn the Enable Control key rightward. After the LCD
changes from EEE to Ad, press Reset on the extinguishant control panel to reset the
extinguishant control panel.
Figure 5-17 Enable Control position
Reset the ejector of the electrical actuator.
Press Reset again to check whether all fire alarms are cleared. After the
alarms are cleared, turn the Enable Control key leftward.