Figure 5-8 Connecting cables to the electromagnetic valve
Step 18 Remove the safety pin after verifying that the fire extinguishing system is working
properly.
Verify that the safety pin is removed after the fire extinguishing system is
commissioned, accepted by the customer, and working properly; otherwise, the
electromagnetic valve may fail to start, and extinguishant may fail to be released
in the case of fire.
1.
----End
5.3 Fire Extinguishing System Commissioning (CE)
Prerequisites
●
●
Issue 01 (2021-04-20)
NO TICE
Remove the safety pin.
Figure 5-9 Removing the safety pin
The extinguishant control panel has been powered on.
The management system is working properly.