Figure 5-14 Opening the cover
Press the test button on the pneumatic switch to short-circuit the cables
inside to simulate an extinguishant release.
Figure 5-15 Pneumatic switch
NO TE
– The extinguishant control panel generates a LOCAL FIRE alarm, and Extinguishant
Release indicator turns on. The warning sign is steady on.
– LOCAL FIRE terminal generates a LOCAL FIRE alarm signal.